Amazon expects record $220 billion in capital spending as AWS secures power early and buys servers later

Amazon expects capital spending to reach about $220 billion in 2026, a company record, with most of the money going toward Amazon Web Services (AWS) and AI infrastructure. AWS chief financial officer John Felton told Business Insider in an email interview that he sees a greater risk in moving too slowly on AI than in investing heavily. That does not mean buying every piece of a data center at once.

Securing land, arranging power and obtaining permits can take years, Felton said, so AWS starts that work early. Land and power can serve different needs over time. Servers are a different decision: AWS waits until a few months before they are due to go online, when customer orders give it a clearer picture of how much capacity to install. If the demand does not materialize, Felton said, AWS does not place the equipment order.

What customer orders tell AWS

Felton said demand was growing faster than AWS could install capacity. He cited multiyear customer contracts as the clearest signal for planning: as of the third quarter of 2026, AWS had a $578 billion backlog of orders, growing at a triple-digit rate. That figure covers AWS orders, not just AI work. Felton also pointed to six consecutive quarters of accelerating AWS growth, with revenue up 39.3% in the latest quarter.

Those measures inform different decisions. Orders help AWS size its buildout; revenue growth, margins and how long investments take to pay back help it judge returns. Felton said AWS expects the assets to generate returns over several years. In his view, customers that already keep applications and data on AWS have a reason to run AI workloads there too, increasing their use of computing power and storage.

A lesson from Amazon’s warehouses

During the pandemic, Amazon doubled the size of a logistics network it had spent 25 years building, Felton said. It later reorganized the US network by region, placing inventory closer to customers to cut fulfillment costs and speed up deliveries. Felton, who spent about two decades in Amazon finance and operations roles before moving to AWS, said that experience shaped both where AWS puts computing capacity and how much it builds against confirmed demand.

Even with signed orders, the constraint on a new data center can shift, Felton said. Once power or permits are secured, the next limiting factor may be chips, memory, networking equipment or optical modules. Delaying server purchases gives AWS room to adjust without postponing the work that takes years.