Samsung reportedly plans Xi’an NAND upgrade, targeting V9 conversion by November 2027

Samsung reportedly plans to upgrade its Xi’an, China, facilities to produce more ninth-generation vertical NAND (V9) for enterprise solid-state drives. Seoul Economic Daily, citing industry sources, says monthly V9 output capacity at the second Xi’an fab, X2, is expected to rise fivefold, from about 10,000 to 50,000 300mm wafers.

Under the reported plan, Samsung would dedicate X2’s upgraded lines to V9 and convert 20–30% of its existing sixth-generation NAND (V6) lines. It also plans to add an electroplating line in unused cleanroom space. Equipment is scheduled to move in around February 2027, with line conversion targeted for completion by November 2027. These are reported plans, not completed upgrades.

Reuters previously reported that Samsung said the upgrade complies with U.S. export regulations and is intended to meet growing global demand, including from U.S. customers, without expanding overall production capacity or building new facilities. The reported fivefold increase concerns V9 capacity at X2, not an announced increase in the site’s total wafer capacity.

According to Seoul Economic Daily’s industry sources, Samsung’s two Xi’an fabs had a combined monthly wafer input capacity of 100,000 as of the second quarter of 2026, compared with 200,000 across its four Pyeongtaek fabs. Xi’an therefore accounted for about one-third of the combined capacity of those two campuses.

Seoul Economic Daily says V9 has 286 layers—50 more than its predecessor—and offers approximately 50% higher TLC storage density and input/output speeds up to 3.2 Gbps, 33% faster. Samsung adopted V9 in its PM1763 enterprise SSD, which entered mass production in July 2026. The report also says yields for some V9 products have reached the low 90% range, versus the low-to-mid 80% range for the previous generation.

The planned shift comes amid demand for AI data-center storage. TrendForce puts Samsung’s share of global enterprise SSD revenue at 35.1% in the second quarter of 2026, ahead of SK hynix Group at 21.1% and Micron at 17.1%. Reuters also reports that SK hynix is seeking to upgrade its Dalian facility from 192-layer NAND to at least 240 layers.